Floor Renovation Project
Floor Renovation Projected Timeline Asbestos Removal: Brock Thermal Inc. Needs one week: October 1st - October 7th Brock Thermal Inc. will remove asbestos RJ Construction from Whitehall WI. 4-5 Weeks to complete: October 8/15 – November 16th We hope to finish mid November. Before snowfall and of course,