Project Update: Gulf Star Marina (1/7/20)
Happy New Year to all! As we usher in 2020 at Gulf Star Marina, we’ve reached a point where all of our structural elements are in place, and the final architectural finishes are underway. The ASAR crane has been assembled, and programming of the automated system will begin this week. The boat lift and finger