Basslink Outage Caused By Exceeding Design Limit
By Corinne Reichert December 20, 2017 The Basslink subsea cable outage of 2015-16 was caused by Basslink (BPL) exceeding its design limit, which then degraded the cable, according to reports by two global experts provided to Hydro Tasmania. The findings on the subsea cable, which provides energy and wholesale high-speed telecommunications services to Tasmania, were made by a